After completing her 30,000+ seater capacity church building situated at Gbagada lagos back in April 2018, which was estimated to cost about $16million
On the last day of the April Easter national retreat of 2019, the church’s general overseer Pst (Dr) W.F Kumuyi declared another vision from God of giving the Deeper Life International Conference Center (DLIC) a new face lift of international standard.
The DLIC is situated along KM 42 lagos-ibadan express way, it is the converging centre for the churchs mega programs like Retreat, leadership strategy congress etc.
Few weeks after the pastor’s announcement, precisely August 2019, a planning committee
was set up and the work on site commenced at a very high pace with the construction of the site office
Major works includes;
1).Construction of a 120,000+ worship center; The worship center comprises of 5 halls, 1 main bowl and a back house building each hall measures about 128*48meters
The work at the worship center is about entering into its final phase, expert says it should be completed before Jan 2022 strategy congress
2) Construction of a pump station
The pump station will provide gas and premium moto spirit for the automobiles in the camp, the construction is almost completed.
3) Construction of the pastor’s lodge
The lodge is a 3 star hotel that will accommodate pastors from all over the world during conventions and other special program. It is a 4 winged structure of about 7 floors each. Construction is currently ongoing
4) Construction of a gigantic female hostel: The members accommodation will not also be left out as the church is on course to build 7 gigantic hostels that will capacity of 8000+ bed spaces
Other projects onsite includes repairs and construction of a the perimeter fencing, construction of a new road network
They work both day and night on site in a quest to beat time
The church is marching forward. The gate of hell will never previal.